Willow Road resurfacing

The 2021 Willow Road resurfacing project is located along Willow Road between Middlefield Road and Chester Street. The scope of work includes dig out repairs, 2.4 inches grinding and asphalt concrete overlay, ADA compliant curb ramps, curb, gutter and striping.

Willow-Road-resurfacing.jpg

Willow Road traffic control

Concrete work at the curb ramps is currently underway. This phase of the project will not require a full closure of Willow Road. There will be minor impacts to traffic with traffic control measures installed, such as cones and signage, to ensure the safety of the workers and general public accessing these areas.

The next phase is grinding and paving work, which is expected to be performed on Fridays and Saturdays only to minimize the impact on traffic along Willow Road. The intention is not to shut down Willow Road, but allow for work to proceed with at least one direction of traffic open to the public at all times, and utilizing a detour. The road will be opened up to traffic by the end of the work day each day.

For information about traffic impacts, view the traffic control plan and/or read and subscribe to the weekly email and text construction news updates.

Contact us

Phillip Linarte

Associate Civil Engineer
Email

650-330-6662

Project schedule


Dates
Work planned
Nov. 29-Dec.3, 2021 Weather permitting, minor impact to traffic as striping work is completed and speed feedback signs are installed.
Nov. 15-24, 2021
Weather permitting, minor impact to traffic as striping operations take place throughout the week. Work to be performed between 8 a.m. and 5 p.m.
Oct. 29-Oct. 30, 2021
Weather permitting, phase 3 of grinding and paving operations to be performed. Willow Road will be open to one way traffic – westbound only 7 a.m.-5 p.m. between O’keefe Street to Middlefield Road. Paving between O’keefe Street to Chester Street along Willow Road has been completed. The intersections of Willow Road/Durham Street and Willow Road/Chester Street will be fully accessible.
Oct. 22-Oct. 23, 2021
Weather permitting, phase 2 of grinding and paving operations to be performed. Willow Road will be open to one way traffic – westbound only 7 a.m.-5 p.m.. VA hospital can be accessed via Willow Road (one way; westbound traffic) and Bay Road.
Oct. 15, 2021
Beginning of grinding operation. All grinding and paving operations to be performed Friday and Saturday
Oct. 1, 2021
6” dig out and plug
Sept. 27-30, 2021
Excavate and plug concrete crosswalks at Willow Road/Gilbert Avenue and Willow Road/Coleman Avenue
Sept. 27-Oct. 10, 2021
O’Keefe Street to Chester Street – ADA curb ramp and concrete work
Sept. 20-24, 2021
Middlefield Road to O’Keefe Street – ADA curb ramp and concrete work
      

Location

90-900 Willow Road, Menlo Park, CA 94025  View map

Google Map